Hard Rock Hotel & Casino
Las Vegas, NV

CLOSE UP DETAIL

Owner

Hard Rock Hotel Holdings

Architect

Klai Juba Architects

Facade Consultant

IBA Consultants

GC

M.J. Dean Construction

Completion

2009

Contract Value

24m

Program

18 and 16-story towers

Building Type

Hospitality / Entertainment / Storefront

Technology Type

Design-Assist, Design-Build

Facade

Design/assist and design/build program for 267,000 sqft of custom twin-span unitized curtainwall, including punched windows, insulation, firesafing, smoke-seal, composite aluminum panels, column covers, storefront entrances and glass handrails

Glass

1/4 HS x 1/2 air x 1/4 FTHS; Viracon VRE11-38; VRE11-42; VRE5-59

Description

Two tower expansion of the Las Vegas Strip’s famed music-themed resort

With the Las Vegas entertainment district outgrowing the Strip, the $1.2 billion Hotel & Casino expansion showcases a stylized resort with a new sense of elegance. The music-themed retreat sits two blocks off Las Vegas Boulevard and is undergoing a 1,200 room expansion of hotel and residential condominiums in two towers standing 16 and 18-stories tall.

Significant design changes were made to the curtainwall and parapet system from the bid documents. Working closely with the owner, architect, structural engineer and general contractor, the Enclos team was able to incorporate these changes into production drawings even before design documents were updated and issued. This action allowed the general contractor to maintain their schedule commitments in spite of the changes. Engineering and material procurement were expedited and Enclos field crews were able to start installation a mere six months from the firm’s original notice-to-proceed on the project.

The curtainwall system creates a patterned facade effect by using four different panel materials: three glass types and an aluminum infill panel. Lighting is integrated into the system to illuminate the curtainwall parapet. Typical double-span units were in 54 and 60 inch widths, each with six framed panels; two vision glass panels and a spandrel glass panel for each floor.

Accelerated schedule requirements and complex site logistics called for an innovative installation strategy. As this was an expansion project, the existing resort operations were ongoing and could not be interfered with. Fabrication sequencing and offsite storage provided for just-in-time delivery of assembled units to the jobsite. Installation crews worked at night using a tower crane that lifted units from a nearby staging area. A clockwise bottom-up wrap, covering two-stories with each level of units, proved optimum and resulted in a schedule that exceeded project expectations throughout the erection process.

<< San Francisco International Airport

Benaroya Hall >>